The Schedule — importing from P6, the critical path, and the data date
Where: open a project, then Schedule in the left menu.
The tabs
Overview, Schedules, P6 Import/Export, PF Activities, PF Resources, Critical Path, EVM, Visualization, PF Calendars and PF Utilization. Resource leveling is not available yet, so the PF Leveling tab is not shown. The Assignments, Team, Conflicts, SOQ and Analytics tabs have been removed; they had no content.
Importing a P6 schedule
- Press Import P6 on the Overview (or Import P6 File on the P6 Import/Export tab) and choose your schedule file: .xer, or P6 XML (.xml, .pmxml).
- Check the preview and the Import Options (relationships, resources, baselines).
- Start the import. A large schedule can take up to a minute; the dialog shows that it is working until the import finishes.
What comes in: the activities, their links, the WBS (with the same dotted WBS codes P6 shows), and, from an .xer file, the schedule's data date. You become a member of the new project, so you can recalculate it straight away.
The Critical Path tab
The tab reads the same activities the Gantt draws.
- The summary row: how many activities are critical, how many are near-critical (5 working days of float or less), Float computed (how many activities have a float value yet), and the schedule's early finish.
- Critical path: the critical activities in order of their early start, each with its ID, early start, early finish, total float in days and progress.
- Near-critical: activities with a little float, smallest float first. Watch these: a short slip puts them on the critical path.
- Source: where an activity's critical flag came from. From file means the imported schedule file gives it a total float of 0, or none at all. PF did not compute it, and it isn't P6's own critical setting. PF CPM means PF computed it at the last recalculation, from the links that came with the import or AI sequencing. Links drawn on the chart aren't included. Recalculate replaces a flag from the file, and so does changing a calendar; the imported flag is not kept.
On the chart, the legend under the toolbar says what the red means, in the words of what is on that chart: a red outline is from the file, solid red on an activity is PF's, and solid red on a task is a flag stored on the task, which PF doesn't compute. My Schedule and Team Schedule show tasks only, so their red is always that stored flag. A red link means both of its ends are flagged, and drawing a link doesn't change what's flagged.
If some activities show not computed for float, the amber note says how many. They are not counted as critical until the schedule is calculated; press Recalculate (below).
The data date
The data date is the "as of" date of a progressed schedule. Work before it is history; work after it is the plan. The bar at the top of the Critical Path tab shows:
- Data date — the current date, and where it came from: (from the P6 file) after an import, or (set here) when you changed it. Not set means the schedule is calculated from the planned start and actual progress is not applied.
- Change data date — pick a new date.
- Progressed work — how started-but-unfinished work is scheduled:
- Retained logic (the default, as in P6) — unfinished work still waits for its predecessors.
- Progress override — a started activity ignores its predecessors.
- Recalculate — saves the date and the choice, recalculates the schedule, and reloads the activities. Finished work keeps its actual dates; unfinished work is scheduled from the data date.
Common questions
Why does my imported schedule start today instead of on the P6 data date? The data date was not set (an XML import does not bring one). Check the bar on the Critical Path tab; set the date and press Recalculate.
Why does an activity say P6 flag but the platform disagrees after I recalculate? After Recalculate the flag shows PF CPM, the platform's own result. Small differences from P6 can come from calendars and settings the two programs read differently.
Where did the Conflicts or Analytics tab go? They were removed because they never showed anything.
Who can link two activities on the chart? Anyone who can edit both of them. A project member can link two tasks of the same project with any of the four types: Finish-to-Start, Start-to-Start, Finish-to-Finish or Start-to-Finish. You can link your own personal tasks in the project, but not someone else's. Both ends must be in the same project.
I drew a link and it said "Not linked". The link was not stored, and the message gives the reason. Before November 8, 2026, a project member who was not also a member of the company's organization could save only Finish-to-Start links: the other three types were not stored. That is fixed. If you still see it, check that both tasks are in the same project and that you can open both.