Inspector Daily Report to Project Closeout
The complete inspector workflow from creating a daily report in the field through compiling the project closeout package. Same workflow whether you're working on a state DOT contract (IDOT, CDOT, future state DOTs) or a private contract — the system uses agency-pluggable renderers to give you the right format at every output without rewriting any data.
Skill level: First-day-on-the-platform inspector to seasoned RE. Time to read: ~10 minutes. Time to do (full closeout cycle): minutes per day, hours at project end.
Finding an older report. The daily report list shows one month at a time. Use the arrows beside the report count to step back or forward a month.
A draft isn't signed. A draft's PDF says Not Signed on the inspector line until the report is submitted, unless you've drawn your signature on it.
What you'll build
1. Project (your contract)
↓
2. Schedule of Quantities (SOQ) (pay items + estimated quantities)
↓
3. Daily Inspector Report (IDR) (each day's work)
↓ pay item entries with quantities
↓ (optional) calculation canvases backing the quantities
↓ submit + accept
4. Q-Book entries auto-post (cumulative quantity ledger)
↓
5. Closeout deliverables (one click each)
├─ Daily IDR PDF (BC 628 or Modern)
├─ IDR Book — date-range compilation (BC 628 grid or Modern)
├─ Q-Book / Quantity Book PDF (BC 625 IDOT or Modern)
└─ Calc Appendix (bound after the Q-Book ledger)
Every output stays current automatically. Add a new IDR, accept it, re-export — the new entries appear immediately. No regeneration buttons, no caches.
Step 1 — Create a project
Where: Dashboard → Projects → + New Project
Required fields:
- Project name (e.g., "I-57 Bridge Deck Replacement", "Route 47 Resurfacing")
- Project code (your internal identifier)
Optional but useful:
- Agency — pick IDOT, CDOT, or other state DOT to unlock agency- specific atlas content (specs, construction manual, Part C documentation requirements, approved vendors). Leave blank for private contracts.
- Address, contract no., job no., district, route, section, county — populate the IDOT BC 623 cover when you export the Quantity Book.
Behind the scenes: the project gets a created_by user and a
project_members row so it appears in your dashboard project list.
Inspectors you add later through the Team tab can pick up
inspector_number, inspector_initials, and inspection_role
(Inspector / Inspector of Record / Senior Inspector) — those flow into
BC 628 signature blocks and IDR Book inspector rosters.
Step 2 — Load the Schedule of Quantities (SOQ)
The SOQ is the contract's pay item list — every line item, with its description, unit, and estimated quantity. PFL ingests it from any of:
- PDF / scanned bid tabulation — the SOQ ingestion reads the pay items off the page (vision + spatial parsing) and recognises the state DOT format on its own
- Excel / CSV upload — direct mapping
- Manual entry — for small projects or change orders
Where: Project → SOQ → Upload (or + Add Pay Item for manual)
For state DOT projects, the system cross-references your pay items
against the agency catalog (agency_pay_item_catalog) and the chain
walk picks up parent agencies — so a Cook County (CDOT) project
automatically inherits IDOT's specifications and construction manual
content for shared sections.
At the end of this step: each pay item has a code, description, unit, and estimated quantity. The atlas modal (Compass icon next to any pay item) opens its full specification, construction manual procedures, documentation requirements, and approved vendors.
Step 3 — Create the Daily Inspector Report (IDR)
Where: Project → Daily Reports → + New Daily Report (or via
the + Daily Report shortcut on your installed PFL app — long-press
the home-screen icon).
The Create Daily Report modal has tabs that vary by report type:
- Standard IDR — full set: General, Work, Personnel, Equipment, DMT, Pay Items, Issues, Inspection, Drawings, Photos, Checksheets
- Daily Report (BC 628 / agency-form mode) — General, DMT, Pay Items, Issues, Inspection, Drawings, Photos, Checksheets
- Diary (RE narrative) — General, Activities, Personnel, Equipment, Issues, Drawings, Photos
The General tab (every mode)
- Date + Time start/end + Break duration
- Weather — high/low temp, conditions, wind, precipitation
- GPS / location verification — captured automatically on mobile
- Site Status at End of Shift — where you left the site (barricades, flaggers, closures). Tap the mic icon to dictate. The Web Speech API + Claude transcript cleanup runs in the browser; no data leaves your device until you save.
- Daily Checklist — Y/N flags for Public Way Closure, Flagging Issues, MOT Issues, Safety, Quality, Materials Delivered, Testing/Inspection, Design Issues, Erosion Control, Utility Conflicts, Extra Work/T&M
The Work tab (Standard / Diary modes)
- Work Performed Summary — the day's narrative. Tap mic to dictate.
- Key Accomplishments — milestones (one per line)
- Next Day Plans — what tomorrow looks like
The Pay Items tab (Standard / Daily Report modes)
This is the heart of the report. Add pay item entries:
- Click + Add Pay Item Entry — auto-complete from the project's SOQ.
- Enter quantity placed today
- Location (e.g., "Sta 12+50 to 14+00, south half")
- Work description (free-text)
- Evidence of Material — agency form codes (BC 981, PRR, etc.)
- Fund Code — for federally-participating items
- Quantity classification —
estimated(default) orfinal(locks the quantity at closeout) - (Optional) Calculation canvas — link a canvas that derives the quantity from station survey data, cross-section areas, etc. The canvas content (variables, equations, derivation steps) is later bound into the Q-Book Calc Appendix as proof.
Open the Atlas from any pay item
Click the Compass icon next to any pay item to see:
- Tier 1 — Project Specification (DS sections from your contract's special provisions)
- Tier 2 — Organization Standard (your firm's reusable specs)
- Tier 3 — Agency Standard (e.g., IDOT Standard Specifications for that pay item's section)
- Documentation Requirements (what forms to file, evidence needed — IDOT's Part C / Documentation Guide)
- Construction Manual procedures (inspection methods, measurement, acceptance criteria)
- Approved Vendors (Qualified Products List entries scoped to the pay item's section)
The atlas walks the agency parent chain automatically — a CDOT project's atlas surfaces IDOT content where CDOT inherits.
Photos + Drawings
- Photos auto-upload to S3 the moment you select them. No need to submit the form first — the system creates a draft to hold them.
- Drawings tab pulls from the project's Plan Sets (
plan_pagestable) and lets you mark up specific pages with annotations tied to the report.
Sign + submit
- Inspector signature (drawn or pre-saved)
- Optional supervisor signature
- Submit moves the report to "submitted" state — visible to the RE / supervisor for review
Finding a report later
The search box above the Daily Reports list reaches past the report name. Type two or more characters of a pay item code or description, a note about the work, a contractor, a piece of equipment, a material ticket number, a delivery or a truck tap session, and the reports that carry it come up — each one labelled with what matched (pay item, activity note, contractor …), so you can see why it is in the list. Status, date range and weather still narrow the list on top of the search.
Step 4 — Accept the IDR (the auto-post moment)
Who: RE, supervisor, or anyone with project_role ≥ inspector_of_record.
Where: Project → Daily Reports list → click the report → Accept
When you click Accept, the daily-report state machine flips
approval_status to accepted and runs autoPostFromReport:
For each pay_item_entry on the report:
1. Look up the most recent calc canvas linked to this pay item
(via calculation_sheets.linked_pay_items @> [pay_item_id])
2. INSERT into quantity_book_entries with:
- source_pay_item_entry_id (canonical link back to the IDR)
- source_calculation_canvas_id (if a calc was linked)
- source_document_reference ("BC 628 #IDR-001, dated 2026-04-25")
- quantity, location, classification (estimated/final)
3. Update pay_item_entries.posted_to_qbook_at + posted_qbook_entry_id
so the IDR knows the Q-Book accepted its quantities
Never double-posts. Re-accepting a report (for example after a revision was requested and the report re-accepted) replaces the earlier posting rather than adding to it; a retry that lands on a half-finished posting is ignored, not repeated.
You should see: the Q-Book page (Project → Quantity Book) now
shows your daily quantity rolled up onto each pay item's progress bar.
The Recent Activity tab shows every entry with its source IDR
reference.
Step 5 — The Quantity Book
Where: Project → Quantity Book (or long-press the PFL home-
screen icon → "Quantity Book")
What's on the page:
- KPIs — total pay items, posted vs estimated, % progress, items marked final
- Pay Items table — one row per pay item with progress bar, total posted, classification badge (Estimated / In Progress / FINAL)
- Recent Activity — flat ledger across the project, latest 50 entries, each with date / pay item / location / qty / source IDR
- Atlas trigger — Compass icon on every pay-item row + clickable pay-item code in Recent Activity opens the same atlas modal
Per-pay-item ledger
Click any pay item row → opens the ledger dialog with every dated entry, cumulative "To Date" computed at read-time via window function (never stored — drift-immune).
Actions in the ledger:
- + Add Entry — manual / authorization adjustment / force account / plan quantity entries (entries that didn't come from an IDR)
- Open Atlas — same modal as the table-row Compass icon
- Mark FINAL — locks the cumulative quantity, sets the badge
- Delete entry — soft-delete, audit-logged
Re-export anytime
- Modern PDF — clean PFL house style, agency-neutral. For private contracts or your own internal records.
- BC 625 PDF — IDOT closeout format with BC 623 title page + BC 624 index of sheets + BC 625 per-pay-item dated ledger pages.
Both exports include the Calc Appendix at the end (opt out with
?appendix=false):
- A divider page ("CALCULATION APPENDIX — N Calculation Sheet(s)")
- One page per linked calc canvas:
- Pay item code(s) + description at top
- Calc title + description
- Variables (key/value pairs from the canvas)
- Calculation content (equations, derivation steps, result)
- "Used by" footer — every IDR # + date + qty + location that drew on this calc to post to the Q-Book
This is the bidirectional cross-reference loop: every Q-Book row points to its source IDR + calc page; every calc page lists every IDR that used it.
Step 6 — Project closeout deliverables
When the project ends, four documents come out — each with one click, each agency-format-aware:
Single Daily IDR
Daily Reports → the report → Export PDF, in one of three layouts:
- Standard — Modern narrative layout (default for Diary mode)
- Agency form — for IDOT projects this is the BC 628 grid (per-item accountability with measured/calculated/checked/inspected-by signature blocks)
- Enhanced — compliance-enhanced version with extra QA fields
Multi-Inspector Aggregated Daily Report (one date, N inspectors)
Daily Reports → the date → Export aggregated PDF.
When multiple inspectors filed separate IDRs for the same date, this compiles them into one PDF: cover with consolidated weather + contractor rollup + Yes/No flags, then per-inspector sections, then optional consolidated summary.
IDR Book — date-range project compilation
Daily Reports → IDR Book → pick the date range and the style.
The closeout book of every approved IDR for a project (or a date range subset). Two visual styles, same data:
- Modern — cover with project + date range + inspector roster + stats; TOC indexed by date → page; per-day separator + IDR content
- BC 628 (IDOT) — agency-style cover with BC 623-shaped project metadata grid; BC 624-style gridded TOC with continuation-page re-renders; minimal per-day separator with form BC 628 footer; per- day pages use the BC 628 grid layout
Soft-fails per-day errors so a single broken IDR doesn't kill the whole book.
Quantity Book
Quantity Book → Export → Modern or BC 625. See Step 5. Either export can leave the Calc Appendix out when you want a lean Q-Book.
Two demo paths to learn from
The platform ships with two staging demo projects covering both agency-aware and agency-neutral usage:
Demo IDOT Resurfacing — Route 47 (Lien Validation)
- Project ID:
d1d0fde0-1d07-4ee0-a000-1d0700000001 - IDOT-linked, IDOT pay item codes (20200100 EARTH EXCAVATION, 35101100 AGGREGATE SUBGRADE, 70200100 TRAFFIC CONTROL, etc.)
- 1 accepted IDR (IDR-001, 2026-04-25), 3 pay item entries, 1 calc canvas linked to Earth Excavation (Sta 12+50 to 14+00 cut volume), 3 Q-Book entries (one with calc canvas reference)
- Use this to demo: BC 628 daily, BC 625 closeout with Calc Appendix, IDR Book BC 628, atlas with full IDOT chain walk
General / Private Contractor demo
Build your own. Skip the agency assignment on project creation. Use generic bid item codes (P-001, P-007, etc.). Same workflow steps — the system routes you into the canonical Modern renderer for every output.
Use this to demo: Modern daily IDR, Modern Q-Book + Calc Appendix, IDR Book Modern, atlas's "Pattern B" (no-agency) graceful empty state
Working with the AI Assistant
The PFL AI Assistant (Compass icon in the dashboard sidebar, or the assistant) is project-scoped. When you start a chat from a project page, the AI knows about that project's pay items, recent IDRs, Q-Book state, and uploaded provisions.
Useful prompts:
- "What's the cumulative quantity placed on pay item 20200100?"
- "Walk me through how to add a pay item entry to today's IDR."
- "Pull up the IDOT spec for Section 440 hot-mix asphalt surface removal."
- "What documentation do I need to file for QPL-required materials on this project?"
The assistant answers with citations to the underlying source — the spec section, construction manual procedure, or BC 628 line item it read from.
Voice input availability
| Field | Standard mode | Daily Report (BC 628) | Diary |
|---|---|---|---|
| General → Site Status at End of Shift | ✅ | ✅ | ✅ |
| Work → Work Performed Summary | ✅ | — (no Work tab) | ✅ |
| Work → Key Accomplishments | ✅ | — | ✅ |
| Work → Next Day Plans | ✅ | — | ✅ |
| Inspection → Inspector Notes | ✅ | ✅ | — |
Tap the mic icon next to any of those labels. Speak. Tap again to stop. The transcript appends to the textarea (multiple chunks add a space or newline as appropriate). Browser-based — works offline once the page is cached. Falls back gracefully on browsers without Web Speech API.
What happens if you change your mind
- Revise an accepted IDR — click "Request Revision" on the report.
State machine flips back to
revision_requested, removes that report's Q-Book entries, clearsposted_to_qbook_aton its pay item entries. You correct the entries, resubmit, re-accept — fresh Q-Book rows post. - Manual Q-Book correction — edit a Q-Book row directly in the Quantity Book ledger. The auto-post's never-double-post rule protects your manual edits from being overwritten on state-machine retries.
- Delete a calc canvas — the calc's FK on
quantity_book_entriesisON DELETE SET NULL. Your Q-Book history stays intact; the calc reference becomes NULL. The Calc Appendix renderer treats that row as "calc no longer available" without breaking.
Mobile / install on a device
- iOS Safari — Share button → Add to Home Screen
- Android Chrome — Install prompt appears in the URL bar; or menu → Install App
- Desktop Chrome / Edge — Install icon in URL bar
Once installed, the app launches in standalone mode (no browser chrome, full screen). Long-pressing the icon surfaces three quick actions: New IDR, Quantity Book, Pay Item Atlas.
Reference
| Surface | URL pattern |
|---|---|
| Project list | /dashboard/projects |
| Project page | /dashboard/projects/[id] |
| Quantity Book | /dashboard/projects/[id]/quantity-book |
| Pay Item Atlas (public) | /tools/idot-pay-items and per-item: /tools/idot-pay-items/[code] |
Truck Tap — photographing the truck instead of a ticket
On a haul-away, the driver often has no paper ticket; the useful record is the truck itself. Tap the camera on the truck's row and photograph the cab door decal (company name, unit number, USDOT and MC numbers). The scan reads the decal and fills the row from it:
- Truck # — the unit number painted on the cab (for example 301). You can type or correct it; the scan never overwrites a number you entered.
- Notes — one line with the hauler, city, unit number, USDOT and MC numbers and any certification text printed on the door (for example "Hauler: Example Hauling LLC (Anytown, IL) · truck 301 · USDOT 0000000 · MC 000000 — fictional example"). A second scan of the same truck does not add the line twice.
- The photo is kept on the row and labelled Truck photo rather than Scanned, so a truck photo is never mistaken for a ticket and the Ticket # box stays empty until a real ticket is scanned or typed.
Departure is optional. The box sits beside Arrival, the same size; leave it blank if you did not record when the truck left.